Sunset Terrace Project

Description

This project consists of reconstruction of streets, sewers, and water main from 6500 Sunset Terrace to 73rd Street.  Phases 1-4.

Contract Amount

  • $1,497,275.60


Estimated Start Date

  • Phase 1 complete December, 2016
  • Phase 2-4:  Start March 27, 2017


Estimated Completion Date

  • August 31, 2017

Contractor(s)

  • Sternquist Construction, 515-975-3642


Engineer

  • Matt Ferrier and Justin Ernst, Bolton & Menk  515-259-9190


City Staff Project Contact

  • Public Works Director Doug Stone 645-6825

Project Status

  • All work is weather dependent, including heat.
  • The Contractor plans to work Saturdays if weather permits.  All work is weather dependent.


70th Street to 73rd Street

The Contractor will be back filling and grading yards the week of November 20th. Weather depending, the roadway will be open to traffic middle to the end of the week.

68th Street to 70th Street

The Contractor will be back filling and grading yards the week of November 20th. Weather depending, the roadway and driveways will be open to traffic middle to the end of the week.

Klooster, Bolton & Menk, at 563-249-1719. He will assist you with the process.


Additional Resources