College Dr Construction

Project Overview

The street is being reconstructed, minor sanitary sewer work is being done, storm sewers and storm sewer intakes are being added, and portions of the water main are being replaced. The project will begin in April or May and should be finished by the end of November.

5/29/20 Update

For the week of June 1st, the Contractor will continue installing storm sewer on Phase 1 west of the bridge. MidAmerican Energy has workers on site doing utility work on gas services and mains. All work is weather dependent. Please remember to place garbage, recycling and yard waste out at the end of your driveway by 5 PM Thursday for the contractor to pick up. Pickup times are different for each item, so they may not be returned at the same time. Temporary mailboxes will be used until the street is open to traffic. Another reminder, please remove any items located within the street right-of-way (10-12 feet from back of curb) that you want salvaged.

5/22/20 Update

For the week of May 25th, the Contractor will continue installing storm sewer on Phase 1 west of the bridge. MidAmerican Energy has workers on site doing utility work on gas services and mains. All work is weather dependent. Please remember to place garbage, recycling and yard waste out at the end of your driveway by 5 PM Thursday for the contractor to pick up. Pickup times are different for each item, so they may not be returned at the same time. Temporary mailboxes will be used until the street is open to traffic. Another reminder, please remove any items located within the street right-of-way (10-12 feet from back of curb) that you want salvaged.

5/15/20 Update

For the week of May 18th, the Contractor will continue installing storm sewer on Phase 1 west of the bridge. MidAmerican Energy has workers onsite doing utility work on gas services and mains. All work is weather dependent.

Please remember to place garbage, recycling and yard waste out at the end of your driveway by 5 PM Thursday for the contractor to pick up. Pickup times are different for each item, so they may not be returned at the same time. Temporary mailboxes will be used until the street is open to traffic. Another reminder, please remove any items located within the street right-of-way (10-12 feet from back of curb) that you want salvaged. The Contractor will not be salvaging any items.

5/8/20 Update

For the week of May 11th, the Contractor will continue installing storm sewers on Phase 1. MidAmerican Energy has workers on site doing utility work on gas services and mains. All work is weather dependent.

Please remember to place garbage, recycling and yard waste out at the end of your driveway by 5 PM Thursday for the Contractor to pick up. Pickup times are different for each item, so they may not be returned at the same time. Temporary mailboxes will be used until the street is open to traffic. Another reminder, please remove any items located within the street right-of-way (10-12 feet from back of curb) that you want salvaged. The Contractor will not be salvaging any items.

5/1/20 Update

For the week of May 4th, the Contractor will continue installing storm sewer on Phase 1.  MidAmerican Energy has workers on site doing utility work on gas services and mains.  All work is weather dependent.  Please remember to place garbage, recycling and yard waste out at the end of your driveway by 5 PM Thursday for the contractor to pick up.  Pickup times are different for each item, so they may not be returned at the same time.  Temporary mailboxes will be used until the street is open to traffic.  Another reminder, please remove any items located within the street right-of-way (10-12 feet from back of curb) that you want salvaged.  The Contractor will not be salvaging any items

4/24/20 Update

4-24-20-College

For the week of April 27th, the Contractor will begin installing the storm sewer on Phase 1. MidAmerican Energy has workers on site doing utility work on gas services and mains. All work is weather dependent. Please remember to place garbage, recycling and yard waste out at the end of your driveway by 5 PM Thursday for the contractor to pick up. Pickup times are different for each item, so they may not be returned at the same time. Temporary mailboxes will be used until the street is open to traffic. Another reminder, please remove any items located within the street right-of-way (10-12 feet from the back of curb) that you want to be salvaged. The Contractor will not be salvaging any items.

4/17/20 Update

During the week of April 20th, the Contractor will continue removing pavement on Phase 1. Almost all the pavement has been removed west of the bridge, then will begin east of the bridge. They will begin work on the storm sewer west of the bridge in the middle of the week. All work is weather dependent. Please remember to place garbage, recycling and yard waste out at the end of your driveway by 5 PM Thursday for the contractor to pick up. Pickup times are different for each item, so they may not be returned at the same time. Temporary mailboxes will be used until the street is open to traffic. Another reminder, please remove any items located within the street right-of-way (10-12 feet from the back of curb) that you want to be salvaged. The Contractor will not be salvaging any items.

4/10/20 Update

During the week of April 13th, the Contractor will begin removing pavement on Phase 1. All work is weather dependent. Please remove vehicles from driveway by the time given in the notice from Contractor. Please remember to place garbage, recycling and yard waste out at the end of your driveway by 5 PM Thursday for the contractor to pick up. Pickup times are different for each item, so they may not be returned at the same time. Temporary mailboxes will be used moving forward. Another reminder, please remove any items located within the street right-of-way (10-12 feet from back of curb) that you want salvaged. The Contractor will not be salvaged any items.