7/24/20 Road Project Update

2020 road projects twitter

69th Street Project

For the week of July 27th, the Contractor will finish installing storm sewer installation on Phase 1. Grading of the roadway is anticipated to begin the week of August 3rd with paving occurring the week of August 10th. It is anticipated that residents can get in their driveways the week of August 10th or the week of August 17th. All work is weather dependent. Please remember to place garbage, recycling and yard waste out at the end of your driveway by 5 PM Thursday for the contractor to pick up. Pickup times are different for each item, so they may not be returned at the same time. The contractor maybe working on Saturdays through out the project to keep the project on schedule.

If you experience problems or have any questions or concerns specific to your water, please contact the DMWW Project Manager, Carla Schumacher, at 515-323-6227 (office) or cschumacher@dmww.com.

Allison Avenue Project

For the week of July 27th, the contractor will begin roadway grading. The week of August 3rd street paving operations will begin. Driveway installation is anticipated to begin for the week of August 3rd and August 10th and it’s anticipated that residents may start using their driveways the week of August 10th. All work is weather dependent. Please remember to place garbage, recycling and yard waste out at the end of your driveway by 5 PM Thursday for the contractor to pick up. Pickup times are different for each item, so they may not be returned at the same time. Temporary mailboxes will be used until the street is open to traffic. Another reminder, please remove any items located within the street right-of-way (10-12 feet from back of curb) that you want salvaged.

If you experience problems or have any questions or concerns specific to your water, please contact the DMWW Project Manager, Carla Schumacher, at 515-323-6227 (office) or cschumacher@dmww.com.

College Drive Project

For the week of July 27th, the Contractor will be paving the street. Driveway installation is anticipated to begin the week of July 27th and continue into the week of August 3rd. It’s anticipated that residents may start using their driveways the week of August 3rd. All work is weather dependent. Please remember to place garbage, recycling and yard waste out at the end of your driveway by 5 PM Thursday for the contractor to pick up. Pickup times are different for each item, so they may not be returned at the same time. Temporary mailboxes will be used until the street is open to traffic. Another reminder, please remove any items located within the street right-of-way (10-12 feet from back of curb) that you want salvaged.

If you experience problems or have any questions or concerns specific to your water, please contact the DMWW Project Manager, Carla Schumacher, at 515-323-6227 (office) or cschumacher@dmww.com.

University Avenue Project

7-24-20-university-update

During the week of July 27th, the Contractor will finish paving operations. West bound traffic will be closed between 70th Street and 73rd Street. That traffic will be detoured down 63rd Street to I-235 to 73rd Street (follow signed detour route). The detour is anticipated to end the week of August 10th. During this time the entrance off University Avenue to Hy-Vee will be closed until the end of the week. Enter Hy-Vee off the 70th Street entrance. All work is weather dependent. All businesses are open. For everyone’s safety, monitor traffic control changes and no texting while driving. Watch for construction workers and added construction truck traffic. Do NOT follow trucks into work zone.

2020 PCC Patching Project

During the week of July 27th, the Contractor will close 70th Street between Hickman Road and Wilshire Boulevard for street patching work. It’s anticipated that the closure will last until August 10th. Please find an alternate route. For everyone’s safety, monitor traffic control changes and no texting while driving. Watch for construction workers and added construction truck traffic. Do NOT follow trucks into work zone.

North Walnut Creek Streambank Restoration Project

The project is complete with restoration and seeding to begin in August or September. The trail is open.


Facebook Twitter Email

Other News in City News

8-3-20-mask resolution use

City Council Passes Mask Resolution

Posted on: August 4, 2020
2020 road projects twitter

7/31/20 Road Projects Update

Posted on: July 31, 2020
Park Plan draft public comment

Review Park Plan

Posted on: July 31, 2020
city-service-online-thumbnail

City Services Online

Posted on: July 23, 2020
storm water best management program

Stormwater Best Management Program

Posted on: July 23, 2020
7-14-20-construction

University Ave Route Update

Posted on: July 14, 2020
canceled storytime in the park summer 2020

Storytime in the Park Canceled

Posted on: July 6, 2020
2020 Summer Hours

City Building Summer Hours

Posted on: May 26, 2020
Bike safety rules

Bike Safety Rules

Posted on: April 3, 2020
No wipes in the pipes

No Wipes in the Pipes

Posted on: April 1, 2020
paint cans and trash

New Hazardous Waste Program

Posted on: March 12, 2020