Posted on: September 11, 2020

9/11/20 Road Construction Update

2020 road projects

Allison Avenue 

The anticipated schedule for each stage of the project is in the table below. Please note that these are estimates and may change depending on weather and utility conflicts.

Stage

Anticipated Start

Anticipated Completion

1

---

8/31

2

8/31

10/24

2A

10/26

11/18


Stage 1 (66th Street to the middle of Allison): For the week of September 14th, the Contractor will finish backfilling behind the curb and around driveways and seed the following week. All work is weather dependent.

Stage 2 (middle of Allison to 64th Street): For the week of September 14th, the Contractor will begin sanitary sewer repairs and storm sewer installation (this work is anticipated to take 3 weeks). Please remember to place garbage, recycling, and yard waste out at the end of your driveway by 5 PM Thursday for the contractor to pick up. Pickup times are different for each item, so they may not be returned at the same time. Temporary mailboxes will be used until the street is open to traffic.

Some of the work may be delayed due to wet conditions from the last week of rain.

There are public information forums held by Zoom at 2 PM on Friday afternoons for each project as well: https://us02web.zoom.us/j/89327380827?pwd=VGI3M1VJRjYzdFRmT3c0VHBURTF6dz09.

Click here to view the recording of the weekly public construction meeting. 

City Councilmembers will also be delivering updates to each property affected by the project until construction is completed.

The contracted completion date for the entire project is November 27th. At this time, the contractor is scheduled to hit that target date. The contractor is not contractually obligated to hit each of the target dates for each of the phases. The dates listed above are to serve as references. We will communicate changes in these dates should they arise.

If you have questions about this project, please contact any of the people at the bottom of this page.

69th Street 

The anticipated schedule for each stage of the project is in the table below. Please note that these are estimates and may change depending on weather and utility conflicts.

Stage

Anticipated Start

Anticipated Completion

1

---

9/5

2

9/14

11/3

3

Possibly spring 2021

Possibly spring 2021

4

Spring 2021

Spring 2021


Stage 1: For the week of September 8th, the Contractor will begin restoration work including backfilling and seeding. Residents have access to their driveways.

Stage 2: For the week of September 8th, the Contractor will begin pavement and driveway removals. Once the pavement is removed, they will begin working on storm sewer and water services (anticipated to be the end of the week). It is anticipated pipework will take 3 weeks. All work is weather dependent. As a reminder, please remove any items located within the street right-of-way (10-12 feet from the back of the curb) that you want to be salvaged. Please remember to place garbage, recycling, and yard waste out at the end of your driveway by 5 PM Thursday for the contractor to pick up. Pickup times are different for each item, so they may not be returned at the same time.

Stages 3 and 4: on September 8th, the City Council approved Resolution No 2020-110 which allows the contractor and engineer to set a reasonable stopping date for the project in the fall of 2020. Due to significant delays from utility companies in phase 1 of the project, the project will not be completed in the fall of 2020 as originally planned. The Contractor may not even begin stage 3 this fall, depending on how weather and site conditions are looking as we get closer to finishing stage 2. If they are able to finish stage 3 of the project before the winter sets in, they will do so. The work that is not finished on this project in the fall of 2020 will be finished in the spring and possibly early summer of 2021. More information about the work that will and will not be completed this year will be provided in these newsletters as we get closer to the winter. To see the documentation for Resolution No 2020-110, please check out the City website:  https://www.windsorheights.org/AgendaCenter/ViewFile/Agenda/_09082020-386

If you experience problems or have any questions or concerns specific to your water, please contact the DMWW Project Manager, Carla Schumacher, at 515-323-6227 (office) or cschumacher@dmww.com

There are public information forums held by Zoom at 2 PM on Friday afternoons for each project as well: https://us02web.zoom.us/j/89327380827?pwd=VGI3M1VJRjYzdFRmT3c0VHBURTF6dz09.

Click here to view the recording of the weekly public construction meeting. 

City Councilmembers will also be delivering updates to each property affected by the project until construction is completed.

If you have questions about this project, please contact any of the people at the bottom of this page.

 

College Drive

The anticipated schedule for each stage of the project is in the table below. Please note that these are estimates and may change depending on weather and utility conflicts.

Stage

Anticipated Start

Anticipated Completion

1

---

8/31

2

8/26

10/7

3

8/31

10/20

4

10/20

11/20


Stage 1 (75th Street to Plaza Circle): For the week of September 14th, the Contractor will be will begin restoration work including backfilling and seeding the following week. They will also be installing mailboxes. The tops of the intakes at 76th Street will be installed along with pouring concrete around them.

Stage 2 (73rd Street to 75th Street): For the week of September 14th, the Contractor will be working on the water main and storm sewer. Water will need to be shut off to complete the water main installation, notices will be given to the affected residents. It’s anticipated that road grading work will begin the week of September 28th. All work is weather dependent. Please remember to place garbage, recycling, and yard waste out at the end of your driveway by 5 PM Thursday for the contractor to pick up. Pickup times are different for each item, so they may not be returned at the same time. Temporary mailboxes will be used until the street is open to traffic.

Stage 3 (Plaza Circle to 78th Street): For the week of September 14th, the Contractor will begin installing storm sewer starting at Plaza Circle and working west (it’s anticipated to last 3 weeks). The east half of Plaza Circle will be open for residents to access College Drive. All work is weather dependent. Please remember to place garbage, recycling, and yard waste out at the end of your driveway by 5 PM Thursday for the contractor to pick up. Pickup times are different for each item, so they may not be returned at the same time. Temporary mailboxes will be used until the street is open to traffic.

Some of the work may be delayed due to wet conditions from the last week of rain.

Stage 4: on September 8th, the City council approved Resolution No 2020-110 which allows the contractor and engineer to set a reasonable stopping date for the project in the fall of 2020. Due to significant delays from utility companies, poor soil conditions near the creek, and whether the project will not be completed in the fall of 2020 as originally planned. The contractor may not stage 4 this fall, depending on how weather and site conditions are looking as we get closer to finishing stages 2 and 3. If they are able to finish stage 4 of the project before the winter sets in, they will do so. The work that is not finished on this project in the fall of 2020 will be finished in the spring of 2021. More information about the work that will and will not be completed this year will be provided in these newsletters as we get closer to the winter. To see the documentation for Resolution No 2020-110, please check out the City website:  https://www.windsorheights.org/AgendaCenter/ViewFile/Agenda/_09082020-386.

There are public information forums held by Zoom at 2 PM on Friday afternoons for each project as well: https://us02web.zoom.us/j/89327380827?pwd=VGI3M1VJRjYzdFRmT3c0VHBURTF6dz09.

Click here to view the recording of the weekly public construction meeting. 

City Councilmembers will also be delivering updates to each property affected by the project until construction is completed.

If you have questions about this project, please contact any of the people at the bottom of this page.

University Avenue 

The anticipated schedule for each phase of the first half of the project is in the table below. A map of the phases is found at the end of this letter. Please note that these are estimates and may change depending on weather and utility conflicts. Elder Corp is working on a plan to transition into either Phase 2A or 2B. At this time, they plan to begin work on 2B before 2A.

Phase

Anticipated Start

Anticipated Completion

1C

---

10/16

2A

Possibly Spring 2021

Possibly Spring 2021

2B

10/26

11/27


During the week of September 14th, the Contractor will continue storm sewer installation at 70th Street. Sidewalk construction and restoration will occur on the north side of the roadway between 70th Street and 73rd Street along with electrical work. Once the storm sewer is installed, they will begin roadway grading. Work on traffic signals between 70th Street and 73rd Street will take place next week. The 70th Street intersection is anticipated to be closed until the end of September. All work is weather dependent. All businesses are open. For everyone’s safety, monitor traffic control changes and no texting while driving. Watch for construction workers and the added construction truck traffic. Do NOT follow trucks into work zone.

Some of the work may be delayed due to wet conditions from the last week of rain.

There are public information forums held by Zoom at 2 PM on Friday afternoons for each project as well: https://us02web.zoom.us/j/89327380827?pwd=VGI3M1VJRjYzdFRmT3c0VHBURTF6dz09

City Councilmembers will also be delivering updates to each property affected by the project until construction is completed.

If you have questions about this project, please contact any of the people at the bottom of this page.

PCC Project

During the week of September 14th, work on the bridge approaches over Walnut Creek on 73rd Street will continue with concrete work on the outside lanes in both directions. Traffic will move to the center lanes and work will continue on the outside lanes. Both north and south bound 73rd Street will be reduced to 1 lane in each direction for the duration of the project. For everyone’s safety, monitor traffic control changes. Do NOT follow trucks into the work zone.

If you have questions about this project, please contact any of the following people:

Dave Burgess

Mayor

515-720-9250

dburgess@windsorheights.org


Mike Jones

City Councilmember, Mayor Pro Tem

515-238-5105

Mike.jones@windsorheights.org


Susan Skeries

City Councilmember

515-250-2206

Susan.skeries@windsorheights.org


Threase Harms

City Councilmember

515-975-5299

tharms@windsorheights.org


Joseph Jones

City Councilmember

515-419-1151

Joseph.jones@windsorheights.org


Mike Loffredo

City Councilmember

515-250-1464

Mike.loffredo@windsorheights.org


Dalton Jacobus

Public Works Director

515-645-6825

djacobus@windsorheights.org


Justin Ernst

City Engineer

515-259-9190 x 2786

justin.ernst@bolton-menk.com

 


Facebook Twitter Email

Other News in City News

2020 road projects

9/18/20 Road Project Updates

Posted on: September 18, 2020
back to the future 9-25-20

Movie in the Park

Posted on: September 17, 2020
park plan 9-21-20

Park Plan Update

Posted on: September 17, 2020
GENERIC NEWS

Ordinance No.20-07

Posted on: September 15, 2020
9-21-20 public hearing

9/21/20 Public Hearing

Posted on: September 16, 2020
9-8-20 city council recap

9/8/20 City Council Recap

Posted on: September 10, 2020
2020 road projects

9/4/20 Road Project Updates

Posted on: September 4, 2020
9-4 last day storm cleanup

Last Day of Storm Debris Cleanup is 9/4

Posted on: September 2, 2020
stormc cleanup website

Storm Debris Cleanup Continues

Posted on: September 1, 2020
2020 road projects

8/28/20 Road Project Update

Posted on: August 28, 2020
zoom roads

Weekly Informational Construction Meetings

Posted on: September 18, 2020
pzc opening

Planning & Zoning Commission Opening

Posted on: August 27, 2020
8-17-20 storm cleanup part 2

Storm Debris Cleanup Continues

Posted on: August 26, 2020
2020 road projects

8/21/20 Road Project Update

Posted on: August 21, 2020
report home damage form

Report Storm Home Damage

Posted on: August 20, 2020
groceries

Food Assistance Replacement

Posted on: August 19, 2020
2020 road projects

8/14/20 Road Project Update

Posted on: August 14, 2020
2020 road projects

8/7/20 Road Project Update

Posted on: August 7, 2020

Ordinance No.20-06

Posted on: August 7, 2020
commercial tax abatement

Commercial Tax Abatement

Posted on: August 6, 2020
8-3-20-mask resolution use

City Council Passes Mask Resolution

Posted on: August 4, 2020
2020 road projects twitter

7/24/20 Road Project Update

Posted on: July 24, 2020