News Flash

City News

Posted on: November 13, 2020

11/13/20 Road Project Update

2020 road projects

College Drive

The anticipated schedule for each stage of the project is in the table below. Please note that these are estimates and may change depending on weather and utility conflicts.

Stage

Anticipated Start

Anticipated Completion

1

---

8/31

2

8/26

11/23

3

8/31

11/23

4

11/2

11/27

 

Stage 2 (73rd Street to 75th Street):  For the week of November 16th, the Contractor will be work on remaining sidewalk.  They will also continue backfilling and cleaning up the site.  Final grading may not occur until the spring along with seeding.  All work is weather dependent.  Please remember to place garbage, recycling and yard waste out at the end of your driveway by 5 PM Thursday for the contractor to pick up.  Pickup times are different for each item, so they may not be returned at the same time.  Temporary mailboxes will be used until the street is open to traffic.

Stage 3 (Plaza Circle to 78th Street):  For the week of November 16th, the Contractor will be pouring intersections and driveways and sidewalks.  They will begin backfilling once all concrete work is completed.  Final grading may not occur until the spring along with seeding.  All work is weather dependent.  Please remember to place garbage, recycling and yard waste out at the end of your driveway by 5 PM Thursday for the contractor to pick up.  Pickup times are different for each item, so they may not be returned at the same time.  Temporary mailboxes will be used until the street is open to traffic.

Stage 4 (78th Street to Harbach Blvd):  Work on Stage 4 is anticipated to begin the week of November 16th.  The Contractor will be putting out door hangers closer to the start date to inform property owners of the start date.  As a reminder, please remove any items located within the street right-of-way (10-12 feet from back of curb) that you want salvaged).  This work is weather dependent.

If you experience problems or have any questions or concerns specific to your water, please contact the DMWW Project Manager, Carla Schumacher, at 515-323-6227 (office) or cschumacher@dmww.com.  

There are public information forums held by Zoom at 2 PM on Friday afternoons for each project as well: https://us02web.zoom.us/j/89327380827?pwd=VGI3M1VJRjYzdFRmT3c0VHBURTF6dz09

City Councilmembers will also be delivering updates to each property affected by the project until construction is completed.

If you have questions about this project, please contact any of these people.


69th Street Update

The anticipated schedule for each stage of the project is in the table below. Please note that these are estimates and may change depending on weather and utility conflicts.

Stage

Anticipated Start

Anticipated Completion

1

---

9/5

2

9/14

11/20

3

Spring 2021

Spring 2021

4

11/17*

12/8*

*phasing is dependent on winter weather conditions. The contractor will not begin stage 4 if forecasted temperatures would not allow paving operations to continue.

Stage 2: For the week of November 16th, the Contractor will begin grading sidewalks and driveways once the street concrete has cured property to allow for traffic.  All work is weather dependent.  Please remember to place garbage, recycling and yard waste out at the end of your driveway by 5 PM Thursday for the Contractor to pick up.  Pickup times are different for each item, so they may not be returned at the same time.

Stage 4:  For the week of November 16th, the Contractor will continue water main work and may begin installing of water services later in the week.  Notices will be given for planned water shut offs to those affected residents.  This work is weather dependent.

If you experience problems or have any questions or concerns specific to your water, please contact the DMWW Project Manager, Carla Schumacher, at 515-323-6227 (office) or cschumacher@dmww.com.  

There are public information forums held by Zoom at 2 PM on Friday afternoons for each project as well: https://us02web.zoom.us/j/89327380827?pwd=VGI3M1VJRjYzdFRmT3c0VHBURTF6dz09

City Councilmembers will also be delivering updates to each property affected by the project until construction is completed.

If you have questions about this project, please contact any of these people.


Allison Avenue Updates

The anticipated schedule for each stage of the project is in the table below. Please note that these are estimates and may change depending on weather and utility conflicts.

Stage

Anticipated Start

Anticipated Completion

1

---

8/31

2

8/31

11/18

2A

11/16

11/30

 

Stage 2 (middle of Allison to 64th Street):  For the week of November 16th, the Contractor will continue concrete work including driveways.  Please remember to place garbage, recycling and yard waste out at the end of your driveway by 5 PM Thursday for the Contractor to pick up.  Pickup times are different for each item, so they may not be returned at the same time.  Temporary mailboxes will be used until the street is open to traffic.

Stage 2B (64th St Intersection):  For the week of November 16th, the Contractor will begin removing pavement along with installing storm sewer.  The intersection will be closed starting Monday morning.  Notices have be given to residents in the area.  Signs have also be installed informing users of the closure.  Please find alternate routes.  Please remember to place garbage, recycling and yard waste out at the end of your driveway by 5 PM Thursday for the contractor to pick up.  Pickup times are different for each item, so they may not be returned at the same time.  Temporary mailboxes will be used until the street is open to traffic.

If you experience problems or have any questions or concerns specific to your water, please contact the DMWW Project Manager, Carla Schumacher, at 515-323-6227 (office) or cschumacher@dmww.com.  

There are public information forums held by Zoom at 2 PM on Friday afternoons for each project as well: https://us02web.zoom.us/j/89327380827?pwd=VGI3M1VJRjYzdFRmT3c0VHBURTF6dz09

City Councilmembers will also be delivering updates to each property affected by the project until construction is completed.

If you have questions about this project, please contact any of these people.

 

University Ave

The anticipated schedule for each phase of the first half of the project is in the table below. A map of the phases is found at the end of this letter. Please note that these are estimates and may change depending on weather and utility conflicts. Elder Corp is working on a plan to transition into either Phase 2A or 2B. At this time, they plan to begin work on 2B before 2A.

Phase

Anticipated Start

Anticipated Completion

1C

---

10/26

2A

 Spring 2021

Spring 2021

2B

10/26

11/27

 

During the week of November 16th, the Contractor will finish pouring the south side of the 70th Street intersection.  Work on traffic signals between 70th Street and 73rd Street will take place along with work on street lighting.  Work is weather dependent.  All businesses are open.  For everyone’s safety, monitor traffic control changes and no texting while driving.  Watch for construction workers and the added construction truck traffic.  Do NOT follow trucks into work zone.

There are public information forums held by Zoom at 2 PM on Friday afternoons for each project as well: 

https://us02web.zoom.us/j/89327380827?pwd=VGI3M1VJRjYzdFRmT3c0VHBURTF6dz09

City Councilmembers will also be delivering updates to each property affected by the project until construction is completed.

If you have questions about this project, please contact any of these people.

 

Facebook Twitter Email

Other News in City News

12-7-20 city council twitter

12/7/20 City Council Meeting on Zoom

Posted on: November 30, 2020
11-24-20 FAQ

Road Construction FAQ

Posted on: November 25, 2020
12-7-20 public hearing

12/7/20 Public Hearing

Posted on: November 25, 2020
2020 road projects

11/20/20 Road Project Update

Posted on: November 20, 2020
11-16-20 city council recap

11/16/20 City Council Recap

Posted on: November 18, 2020
city of windsor heights street

Governor Issues Statewide Mask Mandate

Posted on: November 16, 2020
city of windsor heights neighborhood

Intersection of Allison Ave & 64th Closed

Posted on: November 16, 2020
11-12-20 covid update twitter

Please Do Your Part

Posted on: November 12, 2020
covid testing locations

COVID-19 Testing Near Windsor Heights

Posted on: November 11, 2020
2020 road projects

11/6/20 Road Project Update

Posted on: November 6, 2020
november newsletter

The November Newsletter Is Now Available

Posted on: November 5, 2020
2020 road projects

10/30/20 Road Project Update

Posted on: October 30, 2020
park restrooms closed

Park Restrooms Closed for the Winter

Posted on: November 9, 2020
2020 road projects

10-23-20 Road Project Update

Posted on: October 23, 2020
10-19-20 city council recap

10/19/20 City Council Meeting Recap

Posted on: October 20, 2020
dog park

Dog Park Parking Reminder

Posted on: October 19, 2020
2020 road projects

10/16/20 Road Project Update

Posted on: October 16, 2020
2020 road projects

10/9/20 Road Project Update

Posted on: October 9, 2020
ermald ash borer

Emerald Ash Borer Tree Removal

Posted on: October 8, 2020
city of windsor heights neighborhood

ORDINANCE NO. 20-08

Posted on: October 8, 2020
10-5-20 city council recap twitter

10/5/20 City Council Meeting Recap

Posted on: October 7, 2020
yard-waste pickup ends 11-28-20

2020 Compost It! Season End 11/28

Posted on: October 7, 2020
windsor heights park plan

Park Plan Update

Posted on: October 6, 2020
2020 road projects

10/2/20 Road Project Update

Posted on: October 2, 2020
2020 road projects

9/25/20 Road Project Update

Posted on: September 25, 2020
glass-container-twitter

Glass Recycling Container in Colby Park

Posted on: September 24, 2020
9-21-20 city council recap

9/21/20 City Council Meeting Recap

Posted on: September 22, 2020
2020 road projects

9/18/20 Road Project Updates

Posted on: September 18, 2020
2020 road projects

9/11/20 Road Construction Update

Posted on: September 11, 2020
2020 road projects

9/4/20 Road Project Updates

Posted on: September 4, 2020
2020 road projects

8/28/20 Road Project Update

Posted on: August 28, 2020