12/4/20 Road Project Update

2020 road projects

69th Street

The anticipated schedule for each stage of the project is in the table below. Please note that these are estimates and may change depending on weather and utility conflicts.

Stage

Anticipated Start

Anticipated Completion

1

---

---

2

---

12/19

3

Spring 2021

Spring 2021

4

Spring 2021

Spring 2021

Stage 2: For the week of December 7th, the Contractor will prepping and pouring sidewalk and driveways.  Once all sidewalks and driveways have been completed, they will begin grading yards.  Final grading will not occur until the spring along with seeding.  All work is weather dependent.  Please remember to place garbage and recycling out at the end of your driveway by 5 PM Thursday for the Contractor to pick up.  Pickup times are different for each item, so they may not be returned at the same time.

Stage 3 & 4:  For the week of December 7th, the Contractor will be installing water services.  With water service installation, residents will experience short disruption to water.  Notices will be given for planned water shutoffs to those affected residents.  Driveways with rock in them will be poured with concrete.  This work is weather dependent.

If you experience problems or have any questions or concerns specific to your water, please contact the DMWW Project Manager, Carla Schumacher, at 515-323-6227 (office) or cschumacher@dmww.com.  

If you have questions about this project, please contact any of these people.

 

College Drive Project  

Stage

Anticipated Start

Anticipated Completion

1

---

---

2

---

 

3

---

11/13

4

Spring 2021

Spring 2021

The anticipated schedule for each stage of the project is in the table below. Please note that these are estimates and may change depending on weather and utility conflicts.

Stage 2 (73rd Street to 75th Street):  For the week of December 7th, the Contractor will finish backfilling and cleaning up the site.  Final grading will not occur until the spring along with seeding.  All work is weather dependent.  Please remember to place garbage and recycling out at the end of your driveway by 5 PM Thursday for the Contractor to pick up.  Pickup times are different for each item, so they may not be returned at the same time.  Temporary mailboxes will be used until the street is open to traffic.

Stag 3 (Plaza Circle to 78th Street):  For the week of December 7th, the Contractor will be backfilling and cleaning up the site and installing mailboxes.  Final grading will not occur until the spring along with seeding.  All work is weather dependent.  Please remember to place garbage and recycling at the end of your driveway by 5 PM Thursday for the Contractor to pick up. Pickup times are different for each item, so they may not be returned at the same time.  Temporary mailboxes will be used until the street is open to traffic.

If you experience problems or have any questions or concerns specific to your water, please contact the DMWW Project Manager, Carla Schumacher, at 515-323-6227 (office) or cschumacher@dmww.com.  

If you have questions about this project, please contact any of these people.

 

Allison Avenue Project

The anticipated schedule for each stage of the project is in the table below. Please note that these are estimates and may change depending on weather and utility conflicts.

Stage

Anticipated Start

Anticipated Completion

1

---

---

2

---

12/5

2A

---

12/19


Stage 2 (middle of Allison to 64th Street):  For the week of December 7th, the Contractor will be backfilling and cleaning up the site.  Please remember to place garbage and recycling out at the end of your driveway by 5 PM Thursday for the Contractor to pick up.  Pickup times are different for each item, so they may not be returned at the same time.  Temporary mailboxes will be used until the street is open to traffic.

Stage 2B (64th St Intersection):  For the week of December 7th, the Contractor will be pouring street pavement.  Once street pavement has time to cure properly, they will be pouring driveways.  The intersection will remain closed (approximately another two weeks).  Please find alternate routes.  Please remember to place garbage and recycling out at the end of your driveway by 5 PM Thursday for the Contractor to pick up.  Pickup times are different for each item, so they may not be returned at the same time.  Temporary mailboxes will be used until the street is open to traffic.

If you experience problems or have any questions or concerns specific to your water, please contact the DMWW Project Manager, Carla Schumacher, at 515-323-6227 (office) or cschumacher@dmww.com.  

If you have questions about this project, please contact any of these people.

 

University Avenue Project

The anticipated schedule for each phase of the first half of the project is in the table below. Please note that these are estimates and may change depending on weather and utility conflicts. 

Phase

Anticipated Start

Anticipated Completion

1C

---

---

2A

 Spring 2021

Spring 2021

2B

---

12/19

3

Spring/Summer 2021

Fall 2021 

During the week of December 7th, the Contractor will be pouring a driveway and sealing the roadway.  They will be backfilling and cleaning up the site.  Electrical work will continue between 70th Street and 73rd Street.  Work is weather dependent.  All businesses are open.  For everyone’s safety, monitor traffic control changes, and no texting while driving.  Watch for construction workers and the added construction truck traffic.  Do NOT follow trucks into the work zone.

If you have questions about this project, please contact any of these people.

 

Facebook Twitter Email

Other News in City News

trash-recycling-pushed-back-twitter

Trash Pickup on Friday

Posted on: January 21, 2021
City Council Recap

1/18/21 City Council Recap

Posted on: January 19, 2021
public works director

Blizzard Warning: Snow Removal Reminders

Posted on: January 14, 2021
city of windsor heights street

MWA Calendar Online

Posted on: January 12, 2021
2021 spring ball rentals online

Spring Season Ball Field Rentals Online

Posted on: January 8, 2021
city of windsor heights january newsletter

January Newsletter Available

Posted on: January 7, 2021
city of windsor heights neighborhood

Pet License Registration Moves Online

Posted on: January 5, 2021
city of windsor heights street

Ordinance No. 20-09

Posted on: December 30, 2020
2020 road projects

12/18/20 Road Project Update

Posted on: December 18, 2020
2020 road projects

12/11/20 Road Project Update

Posted on: December 11, 2020
BCycle station coming to windsor heights

BCycle Station Coming to Colby Park

Posted on: December 10, 2020
city-service-online-thumbnail

City Services Online

Posted on: December 9, 2020
email  text alerts

Sign Up for Text or Email Alerts

Posted on: December 2, 2020
11-24-20 FAQ

Road Construction FAQ

Posted on: November 25, 2020
2020 road projects

11/20/20 Road Project Update

Posted on: November 20, 2020
2020 road projects

11/13/20 Road Project Update

Posted on: November 13, 2020
park restrooms closed

Park Restrooms Closed for the Winter

Posted on: November 9, 2020
ermald ash borer

Emerald Ash Borer Tree Removal

Posted on: October 8, 2020
city of windsor heights neighborhood

ORDINANCE NO. 20-08

Posted on: October 8, 2020
windsor heights park plan

Park Plan Update

Posted on: October 6, 2020