12/18/20 Road Project Update

2020 road projects

Check out our road construction FAQ for common questions about the road construction projects in Windsor Heights.

69th Street

Stage 2: For the week of December 21st, the Contractor will be cleaning up the site and preparing for winter conditions.  Grading and backfilling may occur as weather allows.  Final grading will not occur until the spring along with seeding.  All work is weather dependent.  Please remember to place garbage and recycling out at the end of your driveway by 5 PM Thursday for the Contractor to pick up.  Pickup times are different for each item, so they may not be returned at the same time.

Stage 3 & 4:  For the week of December 21st, the Contractor will be pouring driveways with rock in them.  This work is weather dependent.

Stages 3 and 4 will not be completed until the spring of 2021. On 12/7, the City council approved a change order to allow for 72 working days for stages 3 and 4 to be completed on this project in the spring of 2021. Affected residents will be given as much notice as we can before work begins again in the spring. 

If you experience problems or have any questions or concerns specific to your water, please contact the DMWW Project Manager, Carla Schumacher, at 515-323-6227 (office) or cschumacher@dmww.com.

If you experience problems or have any questions or concerns specific to your water, please contact the DMWW Project Manager, Carla Schumacher, at 515-323-6227 (office) or cschumacher@dmww.com.  

Allison Avenue Project

Stage 2 (middle of Allison to 64th Street):  For the week of December 21st, the Contractor will be backfilling, installing mailboxes, and cleaning up the site.  Please remember to place garbage and recycling out at the end of your driveway by 5 PM Thursday for the Contractor to pick up.  Pickup times are different for each item, so they may not be returned at the same time.  Temporary mailboxes will be used until the street is open to traffic.

Stage 2A (64th St Intersection):  For the week of December 21st, the Contractor will finish pouring street pavement and driveways.  The intersection will be opened Thursday morning, weather dependent.  

College Drive Project

Stage 2 (73rd Street to 75th Street):  Work is complete for the winter.  The Contractor will clean up the site once conditions allow.

Stage 3 (Plaza Circle to 78th Street):  For the week of December 21st, the Contractor will be working on a couple of driveways.  They will clean up the site once conditions allow.

If you experience problems or have any questions or concerns specific to your water, please contact the DMWW Project Manager, Carla Schumacher, at 515-323-6227 (office) or cschumacher@dmww.com.

University Avenue Project

Work is complete for the winter and will resume in the spring.  Miscellaneous work will continue between 70th Street and 73rd Street as weather allows throughout the winter.  Work is weather dependent.  All businesses are open.  For everyone’s safety, monitor traffic control changes, and no texting while driving.  Watch for construction workers and the added construction truck traffic.  Do NOT follow trucks into the work zone.

Facebook Twitter Email

Other News in City News

trash-recycling-pushed-back-twitter

Trash Pickup on Friday

Posted on: January 21, 2021
City Council Recap

1/18/21 City Council Recap

Posted on: January 19, 2021
public works director

Blizzard Warning: Snow Removal Reminders

Posted on: January 14, 2021
city of windsor heights street

MWA Calendar Online

Posted on: January 12, 2021
2021 spring ball rentals online

Spring Season Ball Field Rentals Online

Posted on: January 8, 2021
city of windsor heights january newsletter

January Newsletter Available

Posted on: January 7, 2021
city of windsor heights neighborhood

Pet License Registration Moves Online

Posted on: January 5, 2021
city of windsor heights street

Ordinance No. 20-09

Posted on: December 30, 2020
2020 road projects

12/11/20 Road Project Update

Posted on: December 11, 2020
BCycle station coming to windsor heights

BCycle Station Coming to Colby Park

Posted on: December 10, 2020
city-service-online-thumbnail

City Services Online

Posted on: December 9, 2020
2020 road projects

12/4/20 Road Project Update

Posted on: December 4, 2020
email  text alerts

Sign Up for Text or Email Alerts

Posted on: December 2, 2020
11-24-20 FAQ

Road Construction FAQ

Posted on: November 25, 2020
2020 road projects

11/20/20 Road Project Update

Posted on: November 20, 2020
2020 road projects

11/13/20 Road Project Update

Posted on: November 13, 2020
park restrooms closed

Park Restrooms Closed for the Winter

Posted on: November 9, 2020
ermald ash borer

Emerald Ash Borer Tree Removal

Posted on: October 8, 2020
city of windsor heights neighborhood

ORDINANCE NO. 20-08

Posted on: October 8, 2020
windsor heights park plan

Park Plan Update

Posted on: October 6, 2020